Concourse A Update #17
- July 28, 2023
- / Author Name
- / Concourse A

This week, crews have continued the shoring installation in preparation for tie beam and precast joist installation. This work will continue for another few weeks until complete and precast joists are on site. The contractor has also begun excavation for pile cap installing in the eastern portion of the site.
Next week, crews will continue grading and compaction at gate 2. Placement and finishing of concrete will be completed after hours and will not interfere with airline operations.
The contractor has continued the relocation of utilities in the departure hold room site, with foundation work scheduled in the next few weeks.