Concourse A Update #14


  • June 20, 2023
  • /   Author Name
  • /   Concourse A
Construction site showing concrete columns.

Columns are going up on the east side of the construction site, pictured.

Temporary partitions in the arrival’s baggage claim area have been installed in preparation for utility relocation. Crews will begin working within the enclosed site, relocating utilities above the ceiling in preparation for the new elevator shaft and pedestrian bridge foundation.

Southernmost column and foundation work is set to begin following modification of a fence next to the arrivals baggage carousel. These impacts will be in effect until the first portion of concrete decking is in place.

Water has been used to stop the tracking of debris and dust, while sweepers are being utilized inside of the construction area throughout the day.

A second live camera feed has been added facing the east side of the construction zone. A time lapse video of the project thus far is available for the last day, seven days, and 30 days.