Concourse A Update #15
- June 30, 2023
- / Author Name
- / Concourse A
Crews have begun working in the enclosed arrivals site, relocating utilities above the ceiling in preparation for a new elevator shaft and pedestrian bridge foundation.
On Tuesday, June 20, 2023, crews relocated the eastern construction site fence to allow for the southernmost columns and foundation work to begin. These impacts will be in effect until the first portion of concrete decking is in place, which will occur through the end of September.
Auger piles have begun for the southernmost columns with pile caps and columns following in sequence.
The contractor will be shutting down operations until Wednesday, July 5, 2023 in observance of the Fourth of July holiday.
A Clean New Approach
Improving the Passenger Experience
Travel Tips
United Airlines adds New Service
Robot Enhances Airport Cleaning
EYW Shares Community Update
Allegiant Air adds New Service
Key West International Airport and Concourse A Improvements Update
Monroe County Commissioners Approve Concourse A Project Plans
Taking Off: EYW Hosts Groundbreaking Ceremony For New Concourse