Concourse A Update #13
- June 2, 2023
- / Author Name
- / Concourse A
A second live camera feed has been added facing the east side of the construction zone. A time lapse video of the project thus far is available for the last day, seven days, 30 days or from the beginning.
The next step in the construction process will be the installation of the southernmost portion of columns. These columns, in addition to those already erected, will support the concrete deck of the concourse. Impacts are anticipated to begin Monday, June 12, 2023 and will be in effect until the first portion of concrete decking is in place.
In the hold room, temporary wall partitions are scheduled to go up on the night of Monday, June 5. The walls will act as a barrier between nighttime construction of an elevator shaft and passenger bridge foundation. All work will be completed at night and will not interfere with airline operations.
Crews will be working after hours saw cutting areas of the ramp near parking envelope gates 1, 3, 4 and 5. This work will be after hours and not interfere with daily operations. Apron demolition could begin this month, pending an updated construction schedule.
A Clean New Approach
Improving the Passenger Experience
Travel Tips
United Airlines adds New Service
Robot Enhances Airport Cleaning
EYW Shares Community Update
Allegiant Air adds New Service
Key West International Airport and Concourse A Improvements Update
Monroe County Commissioners Approve Concourse A Project Plans
Taking Off: EYW Hosts Groundbreaking Ceremony For New Concourse