Vertical columns have now been erected on the west side of the construction site with scheduled pours to continue next week. This will continue in sequence until columns and pile caps are complete. Night work has begun to energize the new electrical duct bank. The area will be covered with steel plates during operating hours.
Apron demolition could begin in June, pending an updated construction schedule and resolution of concrete mix designs.
Crews continue working on the deinstallation of artwork in the departure lounge. This work is in preparation for foundation work for the Concourse A pedestrian bridge and a new elevator shaft. This work will take place after hours and will not interfere with airline operations.
New Baggage Claim Carousel Opens
EYW Welcomes Breeze Airways
Smart Technology Highlight Of Concourse A Glass; Curtainwall Nearing Completion
EYW Hosts Topping Off Ceremony For New Concourse A Project
March Brings EYW Passenger Count To New Heights
EYW Maintains Stellar Credit Rating
Record-Breaking December Numbers At EYW; Airline Capacity To Increase 20.8 Percent In Q1
Concourse A Update #19
Concourse A Update #18
Concourse A Update #17
Concourse A Update #16
Concourse A Update #15
Concourse A Update #14
Concourse A Update #13
Concourse A Update #12
Concourse A Update #11
Concourse A Update #10
Concourse A Update #9: Pile Caps Poured
Concourse A Update #8: Construction/Airport Operations Continue Alongside Air Show
Concourse A Update #7: Next UP, Vertical Production Piles
Concourse A Update #6: Happy Family Has Left The Building
Concourse A Update #5: Utilities Ready For Install
Concourse A Update #4
Concourse A Update #3
Concourse A Update #2
Taking Off: EYW Hosts Groundbreaking Ceremony For New Concourse
Monroe County Commissioners Approve Concourse A Project Plans