The title of this article is Concourse A Update #4
- This article was posted on Feb 13, 2023
The following is the full article details:
Installation of temporary dewatering wells is in progress along with the first augers on test piles to confirm design strength.
Foundation work for the Concourse will begin shortly.
Concourse interior.
Concourse interior past security.
Concourse hallway
Concourse interior
Demolition of the concrete apron began in early January to make way for the installation of utilities.
C crates were installed in late 2022 and fully put into use on January 9, 2023.
Concourse A Groundbreaking Ceremony
Airside View
Concourse A Alternate View
Concourse A Interior
Concourse A prospective design
Concourse A Exterior
New Baggage Claim Carousel Opens
EYW Welcomes Breeze Airways
Smart Technology Highlight Of Concourse A Glass; Curtainwall Nearing Completion
EYW Hosts Topping Off Ceremony For New Concourse A Project
March Brings EYW Passenger Count To New Heights
EYW Maintains Stellar Credit Rating
Record-Breaking December Numbers At EYW; Airline Capacity To Increase 20.8 Percent In Q1
Concourse A Update #19
Concourse A Update #18
Concourse A Update #17
Concourse A Update #16
Concourse A Update #15
Concourse A Update #14
Concourse A Update #13
Concourse A Update #12
Concourse A Update #11
Concourse A Update #10
Concourse A Update #9: Pile Caps Poured
Concourse A Update #8: Construction/Airport Operations Continue Alongside Air Show
Concourse A Update #7: Next UP, Vertical Production Piles
Concourse A Update #6: Happy Family Has Left The Building
Concourse A Update #5: Utilities Ready For Install
Concourse A Update #4
Concourse A Update #3
Concourse A Update #2
Taking Off: EYW Hosts Groundbreaking Ceremony For New Concourse
Monroe County Commissioners Approve Concourse A Project Plans