The title of this article is Concourse A Update #3

  • This article was posted on Jan 23, 2023
The following is the full article details:

Early Works Package


What’s commonly referred to as the “Early Works Package” has begun as of early January. This work includes demolition of the concrete apron to make way for the installation of a foundation and utilities for the second-level concourse.

“Passenger tunnels are fully in use, allowing passengers to get to their aircraft and safely transition through the area that is the active construction site,” said Richard Strickland, Director of Airports, at a regular meeting of the Monroe County Board of County Commissioners on January 18.


Construction of the aircraft apron is expected to begin in February or March, Strickland said, while vertical construction will hopefully begin in April.  

{{alt}}

New Baggage Claim Carousel Opens

  • This article was posted on 04 14, 2026
{{alt}}

EYW Welcomes Breeze Airways

  • This article was posted on 06 12, 2025
{{alt}}

Smart Technology Highlight Of Concourse A Glass; Curtainwall Nearing Completion

  • This article was posted on 07 11, 2024
{{alt}}

EYW Hosts Topping Off Ceremony For New Concourse A Project

  • This article was posted on 06 06, 2024
{{alt}}

March Brings EYW Passenger Count To New Heights

  • This article was posted on 04 16, 2024
{{alt}}

EYW Maintains Stellar Credit Rating

  • This article was posted on 02 01, 2024
{{alt}}

Record-Breaking December Numbers At EYW; Airline Capacity To Increase 20.8 Percent In Q1

  • This article was posted on 01 19, 2024
{{alt}}

Concourse A Update #19

  • This article was posted on 10 11, 2023
{{alt}}

Concourse A Update #18

  • This article was posted on 09 01, 2023
{{alt}}

Concourse A Update #17

  • This article was posted on 07 28, 2023
{{alt}}

Concourse A Update #16

  • This article was posted on 07 14, 2023
{{alt}}

Concourse A Update #15

  • This article was posted on 06 30, 2023
{{alt}}

Concourse A Update #14

  • This article was posted on 06 20, 2023
{{alt}}

Concourse A Update #13

  • This article was posted on 06 02, 2023
{{alt}}

Concourse A Update #12

  • This article was posted on 05 19, 2023
{{alt}}

Concourse A Update #11

  • This article was posted on 05 11, 2023
{{alt}}

Concourse A Update #10

  • This article was posted on 05 02, 2023
{{alt}}

Concourse A Update #9: Pile Caps Poured

  • This article was posted on 04 21, 2023
{{alt}}

Concourse A Update #8: Construction/Airport Operations Continue Alongside Air Show

  • This article was posted on 04 13, 2023
{{alt}}

Concourse A Update #7: Next UP, Vertical Production Piles

  • This article was posted on 03 24, 2023
{{alt}}

Concourse A Update #6: Happy Family Has Left The Building

  • This article was posted on 03 17, 2023
{{alt}}

Concourse A Update #5: Utilities Ready For Install

  • This article was posted on 03 02, 2023
{{alt}}

Concourse A Update #4

  • This article was posted on 02 13, 2023
{{alt}}

Concourse A Update #3

  • This article was posted on 01 23, 2023
{{alt}}

Concourse A Update #2

  • This article was posted on 01 20, 2023
{{alt}}

Taking Off: EYW Hosts Groundbreaking Ceremony For New Concourse

  • This article was posted on 11 04, 2022
{{alt}}

Monroe County Commissioners Approve Concourse A Project Plans

  • This article was posted on 08 30, 2022
{{alt}}

Key West International Airport and Concourse A Improvements Update

  • This article was posted on 09 28, 2021