The title of this article is Concourse A Update #2

  • This article was posted on Jan 20, 2023
The following is the full article details: With EYW Construction Underway, Designers Think Outside The Box

While construction has begun on Key West International Airport’s new Concourse A project, passengers will notice something familiar in the construction zone being used in an innovative fashion: C crates.

Arriving and departing passengers each have a designated, 80-foot tunnel made of shipping containers for the transition from the existing hold room to the apron, or in reverse upon arrival.

The idea was the result of a collaboration between construction and design teams who were looking for a way to create a seamless transition while protecting passengers at the same time. The containers were put into use in early January.

“As always, we want to keep our passengers safe. We also wanted to shield them as much as possible from ongoing construction, and the best way to do that was to use this innovative solution,” said Director of Airports Richard Strickland.

While rugged enough for the elements on the outside, the interiors are accessible, well-lit and air conditioned.

{{alt}}

New Baggage Claim Carousel Opens

  • This article was posted on 04 14, 2026
{{alt}}

EYW Welcomes Breeze Airways

  • This article was posted on 06 12, 2025
{{alt}}

Smart Technology Highlight Of Concourse A Glass; Curtainwall Nearing Completion

  • This article was posted on 07 11, 2024
{{alt}}

EYW Hosts Topping Off Ceremony For New Concourse A Project

  • This article was posted on 06 06, 2024
{{alt}}

March Brings EYW Passenger Count To New Heights

  • This article was posted on 04 16, 2024
{{alt}}

EYW Maintains Stellar Credit Rating

  • This article was posted on 02 01, 2024
{{alt}}

Record-Breaking December Numbers At EYW; Airline Capacity To Increase 20.8 Percent In Q1

  • This article was posted on 01 19, 2024
{{alt}}

Concourse A Update #19

  • This article was posted on 10 11, 2023
{{alt}}

Concourse A Update #18

  • This article was posted on 09 01, 2023
{{alt}}

Concourse A Update #17

  • This article was posted on 07 28, 2023
{{alt}}

Concourse A Update #16

  • This article was posted on 07 14, 2023
{{alt}}

Concourse A Update #15

  • This article was posted on 06 30, 2023
{{alt}}

Concourse A Update #14

  • This article was posted on 06 20, 2023
{{alt}}

Concourse A Update #13

  • This article was posted on 06 02, 2023
{{alt}}

Concourse A Update #12

  • This article was posted on 05 19, 2023
{{alt}}

Concourse A Update #11

  • This article was posted on 05 11, 2023
{{alt}}

Concourse A Update #10

  • This article was posted on 05 02, 2023
{{alt}}

Concourse A Update #9: Pile Caps Poured

  • This article was posted on 04 21, 2023
{{alt}}

Concourse A Update #8: Construction/Airport Operations Continue Alongside Air Show

  • This article was posted on 04 13, 2023
{{alt}}

Concourse A Update #7: Next UP, Vertical Production Piles

  • This article was posted on 03 24, 2023
{{alt}}

Concourse A Update #6: Happy Family Has Left The Building

  • This article was posted on 03 17, 2023
{{alt}}

Concourse A Update #5: Utilities Ready For Install

  • This article was posted on 03 02, 2023
{{alt}}

Concourse A Update #4

  • This article was posted on 02 13, 2023
{{alt}}

Concourse A Update #3

  • This article was posted on 01 23, 2023
{{alt}}

Concourse A Update #2

  • This article was posted on 01 20, 2023
{{alt}}

Taking Off: EYW Hosts Groundbreaking Ceremony For New Concourse

  • This article was posted on 11 04, 2022
{{alt}}

Monroe County Commissioners Approve Concourse A Project Plans

  • This article was posted on 08 30, 2022
{{alt}}

Key West International Airport and Concourse A Improvements Update

  • This article was posted on 09 28, 2021