The title of this article is Concourse A Update #17
- This article was posted on Jul 28, 2023
The following is the full article details:
This week, crews have continued the shoring installation in preparation for tie beam and precast joist installation. This work will continue for another few weeks until complete and precast joists are on site. The contractor has also begun excavation for pile cap installing in the eastern portion of the site.
Next week, crews will continue grading and compaction at gate 2. Placement and finishing of concrete will be completed after hours and will not interfere with airline operations.
The contractor has continued the relocation of utilities in the departure hold room site, with foundation work scheduled in the next few weeks.
New Baggage Claim Carousel Opens
EYW Welcomes Breeze Airways
Smart Technology Highlight Of Concourse A Glass; Curtainwall Nearing Completion
EYW Hosts Topping Off Ceremony For New Concourse A Project
March Brings EYW Passenger Count To New Heights
EYW Maintains Stellar Credit Rating
Record-Breaking December Numbers At EYW; Airline Capacity To Increase 20.8 Percent In Q1
Concourse A Update #19
Concourse A Update #18
Concourse A Update #17
Concourse A Update #16
Concourse A Update #15
Concourse A Update #14
Concourse A Update #13
Concourse A Update #12
Concourse A Update #11
Concourse A Update #10
Concourse A Update #9: Pile Caps Poured
Concourse A Update #8: Construction/Airport Operations Continue Alongside Air Show
Concourse A Update #7: Next UP, Vertical Production Piles
Concourse A Update #6: Happy Family Has Left The Building
Concourse A Update #5: Utilities Ready For Install
Concourse A Update #4
Concourse A Update #3
Concourse A Update #2
Taking Off: EYW Hosts Groundbreaking Ceremony For New Concourse
Monroe County Commissioners Approve Concourse A Project Plans