The title of this article is Concourse A Update #17

  • This article was posted on Jul 28, 2023
The following is the full article details:

This week, crews have continued the shoring installation in preparation for tie beam and precast joist installation. This work will continue for another few weeks until complete and precast joists are on site. The contractor has also begun excavation for pile cap installing in the eastern portion of the site. 

Next week, crews will continue grading and compaction at gate 2. Placement and finishing of concrete will be completed after hours and will not interfere with airline operations. 

The contractor has continued the relocation of utilities in the departure hold room site, with foundation work scheduled in the next few weeks. 

{{alt}}

New Baggage Claim Carousel Opens

  • This article was posted on 04 14, 2026
{{alt}}

EYW Welcomes Breeze Airways

  • This article was posted on 06 12, 2025
{{alt}}

Smart Technology Highlight Of Concourse A Glass; Curtainwall Nearing Completion

  • This article was posted on 07 11, 2024
{{alt}}

EYW Hosts Topping Off Ceremony For New Concourse A Project

  • This article was posted on 06 06, 2024
{{alt}}

March Brings EYW Passenger Count To New Heights

  • This article was posted on 04 16, 2024
{{alt}}

EYW Maintains Stellar Credit Rating

  • This article was posted on 02 01, 2024
{{alt}}

Record-Breaking December Numbers At EYW; Airline Capacity To Increase 20.8 Percent In Q1

  • This article was posted on 01 19, 2024
{{alt}}

Concourse A Update #19

  • This article was posted on 10 11, 2023
{{alt}}

Concourse A Update #18

  • This article was posted on 09 01, 2023
{{alt}}

Concourse A Update #17

  • This article was posted on 07 28, 2023
{{alt}}

Concourse A Update #16

  • This article was posted on 07 14, 2023
{{alt}}

Concourse A Update #15

  • This article was posted on 06 30, 2023
{{alt}}

Concourse A Update #14

  • This article was posted on 06 20, 2023
{{alt}}

Concourse A Update #13

  • This article was posted on 06 02, 2023
{{alt}}

Concourse A Update #12

  • This article was posted on 05 19, 2023
{{alt}}

Concourse A Update #11

  • This article was posted on 05 11, 2023
{{alt}}

Concourse A Update #10

  • This article was posted on 05 02, 2023
{{alt}}

Concourse A Update #9: Pile Caps Poured

  • This article was posted on 04 21, 2023
{{alt}}

Concourse A Update #8: Construction/Airport Operations Continue Alongside Air Show

  • This article was posted on 04 13, 2023
{{alt}}

Concourse A Update #7: Next UP, Vertical Production Piles

  • This article was posted on 03 24, 2023
{{alt}}

Concourse A Update #6: Happy Family Has Left The Building

  • This article was posted on 03 17, 2023
{{alt}}

Concourse A Update #5: Utilities Ready For Install

  • This article was posted on 03 02, 2023
{{alt}}

Concourse A Update #4

  • This article was posted on 02 13, 2023
{{alt}}

Concourse A Update #3

  • This article was posted on 01 23, 2023
{{alt}}

Concourse A Update #2

  • This article was posted on 01 20, 2023
{{alt}}

Taking Off: EYW Hosts Groundbreaking Ceremony For New Concourse

  • This article was posted on 11 04, 2022
{{alt}}

Monroe County Commissioners Approve Concourse A Project Plans

  • This article was posted on 08 30, 2022
{{alt}}

Key West International Airport and Concourse A Improvements Update

  • This article was posted on 09 28, 2021