The title of this article is Concourse A Update #16
- This article was posted on Jul 14, 2023
The following is the full article details:
Crews have completed installation of pile caps on the western end of the construction site. Formwork for columns will begin next week with concrete pours scheduled for Tuesday, July 18, and Thursday, July 20. Excavation and preparation for pile cap installation in the eastern portion of the site is expected to begin the week of July 17 continuing through the end of September.
Night work will occur for apron demolition soon.
New Baggage Claim Carousel Opens
EYW Welcomes Breeze Airways
Smart Technology Highlight Of Concourse A Glass; Curtainwall Nearing Completion
EYW Hosts Topping Off Ceremony For New Concourse A Project
March Brings EYW Passenger Count To New Heights
EYW Maintains Stellar Credit Rating
Record-Breaking December Numbers At EYW; Airline Capacity To Increase 20.8 Percent In Q1
Concourse A Update #19
Concourse A Update #18
Concourse A Update #17
Concourse A Update #16
Concourse A Update #15
Concourse A Update #14
Concourse A Update #13
Concourse A Update #12
Concourse A Update #11
Concourse A Update #10
Concourse A Update #9: Pile Caps Poured
Concourse A Update #8: Construction/Airport Operations Continue Alongside Air Show
Concourse A Update #7: Next UP, Vertical Production Piles
Concourse A Update #6: Happy Family Has Left The Building
Concourse A Update #5: Utilities Ready For Install
Concourse A Update #4
Concourse A Update #3
Concourse A Update #2
Taking Off: EYW Hosts Groundbreaking Ceremony For New Concourse
Monroe County Commissioners Approve Concourse A Project Plans